The Southern Beltway: US-22 to I-79Detailed
studies for the Southern Beltway from U.S. Route 22 to Interstate 79 are nearing
completion. Issues raised at the
December 2000 series of public open house meetings and those identified from the
detailed studies for the project, have been evaluated and refinements have been
made to the alternatives being considered for the project. Coordination
with the environmental resource agencies, PENNDOT and the Federal Highway
Administration will occur during the next few months to present the findings of
the detailed studies. Once
this information is reviewed by the appropriate agencies, the Draft
Environmental Impact Statement (DEIS) will be prepared and released for public
review and a public hearing will be held. The
DEIS will present the analysis of the alternatives being evaluated in the
detailed studies: Alternative
B-1, Alternative B-2 and Alternative B-3, as well as the No Build Alternative.
The
release of the DEIS is anticipated for late 2002 or early 2003.
It is expected that a Recommended Preferred Alternatives will be
identified in the DEIS. Following
consideration of the comments received from the DEIS and public hearing, a Final
Environmental Impact Statement (FEIS) will be prepared and circulated for public
comment. After the comments from
the FEIS are evaluated, the Federal Highway Administration will issue a Record
of Decision, which will identify the selected alternative for the project.
Final design, right-of-way acquisition and construction could then begin
for the project, providing that funding is identified for these phases of the
project. |