 | As indicated in the Current Status section,
West Virginia is currently behind Pennsylvania as far as construction and completion
schedules. West Virginia is expected to begin their 4.2 mile section in
Spring 2000 and not complete it until early 2004. This will leave the Pennsylvania section
incomplete until 2004 requiring southbound travelers to exit the expressway prematurely at
Gans Road, the last interchange in Pennsylvania before traveling into West Virginia.
For more information on the West Virginia section, please click here.
|
 | NEW!
Click here for a map of
the West Virginia Section.
|
 | The Mason Dixon Link exceeds traffic expectations; click here
for details.
|
 | The Pennsylvania Turnpike
Commission OPENED the Pennsylvania portion of this project. Click here
for more information.
|
 | Toll schedule for the Mason Dixon Link has been announced
as follows:
| Toll Information
-- Rubles Mill Road Toll Plaza |
Fare |
| Class 1 (2 axle) |
$0.50 |
| Class 2 (3 axle) |
$1.00 |
| Class 3 (4 axle) |
$1.50 |
| Class 4 (5 axle) |
$2.00 |
| Class 5 (6 axle) |
$2.50 |
| Toll Information
-- Mainline Toll Plaza |
Fare |
| Class 1 (2 axle) |
$0.75 |
| Class 2 (3 axle) |
$1.50 |
| Class 3 (4 axle) |
$2.25 |
| Class 4 (5 axle) |
$3.00 |
| Class 5 (6 axle) |
$3.75 |
|
 | Construction Contract Lettings for the
section are as follows (for additional information and details on these contracts, please
see Contract Details):
|
Const. Sect./Status
|
Description
|
Contractor
|
Bid Amount (in Millions)
|
Key Dates
|
50A
Completed |
Fairchance Interchange and Structure for Big Six Road |
Mashuda Corp. |
$3.2 |
Letting Date
October 13, 1994
Completion Date
N/A |
50W
Completed |
Wetland Replacement, Springhill Township |
Swenglish & Sons |
$0.7 |
Letting Date
May 28, 1997
Completion Date
May 28, 1999 |
50C
Completed |
Ruble Mill Interchange, Grading for Mainline Toll Plaza,
3 Dual Mainline Structures, 2 Ramp Collection Facilities and 2.8 Mils of Expressway |
Mashuda Corp. |
$35.3 |
Letting Date
May 29, 1997
Completion Date
November 19, 1999 |
50B
Completed |
Gans Road Interchange and 2.9 Mils of Expressway |
Elmo Greer & Sons |
$26.6 |
Letting Date
September 4, 1997
Completion Date
November 19, 1999 |
50D
Completed |
Paving of Fairchance Interchange, 1 Dual Mainline
Structure and 2.0 Miles of Expressway |
New Enterprise |
$18.5 |
Letting Date
November 6, 1997
Completion Date
November 19, 1999 |
50S
Completed |
Signing - West Virginia/Pennsylvania Line to Fairchance
Interchange |
Green Acres |
$0.7 |
Letting Date
January 7, 1998
Completion Date
November 19, 1999 |
50N
Completed |
1 Mainline Toll Plaza |
Mosites Const Co.
W.G. Tomko & Son
Commelec, Inc. |
$4.4 |
Letting Date
June 17, 1998
Completion Date
September 17, 1999 |
50T
Completed |
Communications Tower |
J.G. Contracting Company |
$0.5 |
Letting Date
February 10, 1999
Completion Date
November 19, 1999 |
50SM
Completed |
Stream Mitigation |
|
$0.1 |
Completion Date
December 2000 |