 | I-68 to Uniontown (Mason Dixon Link) - $11
million for environmental clearance, $24 million for final design and right-of-way
acquisition, $3 million for utility relocations and $107 million for construction. |
 | Uniontown to Brownsville - $13 million for
environmental clearance and $58 million for final design and right-of-way acquisition. |
 | I-70 to PA-51 - $13 million for environmental
clearance, $97 million for final design and right-of-way acquisition, $45 million for
utility relocations and $422 million for construction. |
 | PA-51 to Pittsburgh - $17 million for
environmental clearance and $172 million for final design and right-of-way acquisition. |